Birdscreen installation Reactors
24-Field Engineerd Pipework
Birdscreen installation Reactors
Contractor:
PMF
WP owner:
Wouter
Progress:
Backlog
Finishweek:
44
WP Number:
100711
Description:
Alle High Level Vents in de reactor area dienen te worden voorzien van Bird screens.
Daarnaast dienen tevens de ventgasleidingen vcan de dust filters op de silo's te worden voorzien van Bird screens.
All reactors involved.
Impact on later execution period
Cost impact:
Manhours
Equipment
Others