Modifications on leg's steelreactors
01-Reactor
01-Reactor - 18
Contractor:
Oving
WP owner:
Wouter
Progress:
Progress 25
Finishweek:
36
WP Number:
23
Description:
Modifications on leg's steelreactors regarding guides and crosses
Crosses, at front location are corrected allready
Impact on later execution period
Cost impact:
Manhours
Equipment
Others