Cable installation Substation 3 - MCC 1-6

07-Electrical and instrumentation

07-Electrical and instrumentation - 17

Contractor:

PMF

WP owner:

Progress:

Backlog

Finishweek:

37

WP Number:

493

Description:

Cable installation Substation 3 - MCC

Impact on later execution period

Cost impact:

Manhours
Equipment
Others