Piping into reactor building 19

24-Site Pipework

24 - Cooling water

Contractor:

PMF

WP owner:

Simon

Progress:

Progress 75

Finishweek:

35

WP Number:

858

Description:

Piping into reactor building

Impact on later execution period

Cost impact:

Manhours
Equipment
Others