Workpackages
< Back
ALL
Filters:
Owner
Selecteer Owner
Module
Selecteer Module
Line
Selecteer Line
Status
Selecteer Status
Finishweek
Selecteer Finishweek
Site install
Company
installation O2 analysers
01-05
Simon
Details
Allignment of motor and gearbox
01-04
Simon
Details
E&I connections to/into PU Kristalex
01-05
Simon
Details
Pubpiece to chiller
01-03
Simon
Details
Supporting Electrical Reactor line
01-02
Simon
Details
Modifications on leg's steelreactors
01-02
Simon
Details
E&I connection of motor and gearbox
01-05
Simon
Details
Supporting Piping utilities Reactor line
01-02
Wouter
Details
Pubpiece to chiller
01-03
Wouter
Details
Diverse steel items, not delivered BG
01-02
Simon
Details
installation of explosion hatches
01-04
Wouter
Details
E&I connection of motor and gearbox
01-05
Simon
Details
Reactor Platform over reactor part B (conn. A - mod 2)
01-02
Wouter
Details
Reactor Platform over reactor part B (conn. A - mod 2)
01-02
Wouter
Details
installation O2 analysers
01-05
Gabriel
Details
Diverse steel items, not delivered BG
01-02
Wouter
Details
Diverse steel items, not delivered BG
01-02
Wouter
Details
Supporting Piping utilities Reactor line
01-02
Wouter
Details
Modifications on leg's steelreactors
01-02
Wouter
Details
Supporting Electrical Reactor line
01-02
Wouter
Details
Supporting Piping M02 Reactor line
01-02
Wouter
Details
installation O2 analysers
01-05
Wouter
Details
Supporting Piping utilities Reactor line
01-02
Simon
Details
installation O2 analysers
01-05
Wouter
Details
Reactor Platform over reactor part A
01-02
Simon
Details
Reactor Platform over reactor part B (conn. A - mod 2)
01-02
Simon
Details
Allignment of motor and gearbox
01-04
Wouter
Details
Diverse steel items, not delivered BG
01-02
Wouter
Details
Modifications on leg's steelreactors
01-02
Wouter
Details
installation O2 analysers
01-05
Simon
Details
Pubpiece to chiller
01-03
Simon
Details
Supporting Piping utilities Reactor line
01-02
Simon
Details
Diverse steel items, not delivered BG
01-02
Simon
Details
Reactor Platform over reactor part B (conn. A - mod 2)
01-02
Simon
Details
Allignment of motor and gearbox
01-04
Simon
Details
Insulation of head Reactor 23 PP
01-03
Wouter
Details
Insulation of head Reactor 24 PP
01-03
Wouter
Details
Insulation of head Reactor 17 PP
01-03
Wouter
Details
Installation Flowserve pumps 3x
02-04
Simon
Details
Filling the scrubber with internals 17
02-04
Simon
Details
Installation of HeatExchanger
02-04
Wouter
Details
Prefab piping, incl utility piping 17
02-03
Wouter
Details
E&I connections to/into PU
02-05
Simon
Details
Installation Seepex pumps
02-04
Simon
Details
Prefab piping, incl utility piping
02-03
Simon
Details
Installation Flowserve pumps 3x
02-04
Simon
Details
Installation of instruments
02-05
Simon
Details
Installation Seepex pumps
02-04
Simon
Details
Filling the scrubber with internals 18
02-04
Simon
Details
Piping M02
02-03
Simon
Details
Reactor Platform over reactor part B (conn. A - mod 2)
01-02
Simon
Details
Reactor Platform over reactor part A
01-02
Simon
Details
Supporting Piping utilities Reactor line
01-02
Simon
Details
installation of explosion hatches
01-04
Simon
Details
Supporting Piping M02 Reactor line
01-02
Simon
Details
Diverse steel items, not delivered BG
01-02
Simon
Details
installation O2 analysers
01-05
Simon
Details
Reactor Platform over reactor part A
01-02
Wouter
Details
Supporting Electrical Reactor line
01-02
Wouter
Details
Modifications on leg's steelreactors
01-02
Wouter
Details
E&I connections to/into PU Kristalex
01-05
Simon
Details
Supporting Piping M02 Reactor line
01-02
Wouter
Details
Allignment of motor and gearbox
01-04
Wouter
Details
E&I connections to/into PU Kristalex
01-05
Wouter
Details
Modifications on leg's steelreactors
01-02
Wouter
Details
Allignment of motor and gearbox
01-05
Wouter
Details
Reactor Platform over reactor part B (conn. A - mod 2)
01-02
Wouter
Details
E&I connections to/into PU Kristalex
01-05
Wouter
Details
Reactor Platform over reactor part A
01-02
Wouter
Details
Pubpiece to chiller
01-03
Wouter
Details
Allignment of motor and gearbox
01-04
Wouter
Details
installation of explosion hatches
01-04
Wouter
Details
Pubpiece to chiller
01-03
Wouter
Details
Supporting Piping M02 Reactor line
01-02
Simon
Details
installation of explosion hatches
01-04
Wouter
Details
E&I connections to/into PU Kristalex
01-05
Wouter
Details
E&I connection of motor and gearbox
01-05
Wouter
Details
Supporting Electrical Reactor line
01-02
Simon
Details
Supporting Electrical Reactor line
01-02
Simon
Details
Supporting Piping M02 Reactor line
01-02
Simon
Details
Reactor Platform over reactor part A
01-02
Simon
Details
E&I connection of motor and gearbox
01-05
Simon
Details
E&I connections to/into PU Kristalex
01-05
Simon
Details
Modifications on leg's steelreactors
01-02
Simon
Details
installation of explosion hatches
01-04
Simon
Details
Insulation of head Reactor 20 PP
01-03
Wouter
Details
Insulation of head Reactor 18 PP
01-03
Wouter
Details
Installation Oil filters 2x
02-04
Simon
Details
Installation Chiller
02-04
Simon
Details
Installation Scrubber 17
02-04
Simon
Details
Installation of instruments
02-05
Simon
Details
Hydrotest piping skid
02-03
Simon
Details
Piping M02
02-03
Simon
Details
E&I connections to/into PU
02-05
Simon
Details
Installation Chiller
02-04
Simon
Details
Installation Oil filters 2x
02-04
Simon
Details
Installation Scrubber 18
02-04
Simon
Details
Hydrotest piping skid
02-03
Simon
Details
Installation of HeatExchanger
02-04
Wouter
Details
Installation Chiller
02-04
Simon
Details
8