top of page

Birdscreen installation Reactors

24-Field Engineerd Pipework

Birdscreen installation Reactors

Contractor:

PMF

WP owner:

Wouter

Progress:

Backlog

Finishweek:

44

WP Number:

100711

Description:

Alle High Level Vents in de reactor area dienen te worden voorzien van Bird screens.
Daarnaast dienen tevens de ventgasleidingen vcan de dust filters op de silo's te worden voorzien van Bird screens.

All reactors involved.

Impact on later execution period

Cost impact:

Manhours
Equipment
Others
bottom of page