Hydrolic connection installation

04A-Hydrolic Unit

04A-Hydrolic Unit - 19

Contractor:

PMF

WP owner:

Wouter

Progress:

Backlog

Finishweek:

36

WP Number:

224

Description:

Installation of hydrolic connections

Impact on later execution period

Cost impact:

Manhours
Equipment
Others

04-09-2025 Cooling screw delay of delivery reported. no update of delivery of Slidevalve and cylinders ( is critical)

4 september 2025 om 09:18:22

DJ