Pubpiece to chiller
01-Reactor
01-Reactor - 19
Contractor:
CHEM
WP owner:
Wouter
Progress:
Done
Finishweek:
37
WP Number:
32
Description:
Installation of the pubpiece to chiller and N3.
Will be executed by an Bulgarian company.
INSTALLATION DATE: Week 38
Dear Mr. Nedyalkov,
As we talked over the phone – at construction site in Netherlands will come 2 certified welder and 2 fitters with a team leader with the task to perform welding of reactor N03 nozzle and collar of reactors 19 and 20.
-The activity commence 01 – September – 2025
-You should bring with you welding consumables and welding apparatus
-As we discuss you will arrange the accommodation
Please, the people shall have
https://employment-social-affairs.ec.europa.eu/policies-and-activities/moving-working-europe/eu-social-security-coordination/european-health-insurance-card/how-use-card/bulgaria-european-health-insurance-card_en
Please, send across the welders certificates.
Impact on later execution period
Cost impact:
Manhours
Equipment
Others
PMF is informed that the Flange of the spool piece is DN 400 PN6 and the connection required is DN400 PN 10 Cirtec operations informed that the material required is SS310 and deliverytime is 6 weeks. This is a critical item.
4 september 2025 om 08:43:22
DJ