Pubpiece to chiller

01-Reactor

01-Reactor - 19

Contractor:

CHEM

WP owner:

Wouter

Progress:

Done

Finishweek:

37

WP Number:

32

Description:

Installation of the pubpiece to chiller and N3.

Will be executed by an Bulgarian company.

INSTALLATION DATE: Week 38


Dear Mr. Nedyalkov,

As we talked over the phone – at construction site in Netherlands will come 2 certified welder and 2 fitters with a team leader with the task to perform welding of reactor N03 nozzle and collar of reactors 19 and 20.
-The activity commence 01 – September – 2025
-You should bring with you welding consumables and welding apparatus
-As we discuss you will arrange the accommodation
Please, the people shall have
https://employment-social-affairs.ec.europa.eu/policies-and-activities/moving-working-europe/eu-social-security-coordination/european-health-insurance-card/how-use-card/bulgaria-european-health-insurance-card_en
Please, send across the welders certificates.

Impact on later execution period

Cost impact:

Manhours
Equipment
Others

PMF is informed that the Flange of the spool piece is DN 400 PN6 and the connection required is DN400 PN 10 Cirtec operations informed that the material required is SS310 and deliverytime is 6 weeks. This is a critical item.