top of page
Cable installation Substation 2 - MCC Oil conditioning
07-Electrical and instrumentation
07-Electrical and instrumentation -
Contractor:
PMF
WP owner:
Jaceq
Progress:
Backlog
Finishweek:
38
WP Number:
490
Description:
Cable installation Substation 2 - MCC
Impact on later execution period
Cost impact:
Manhours
Equipment
Others
bottom of page