top of page

Cable installation Substation 3 - MCC 1-7

07-Electrical and instrumentation

07-Electrical and instrumentation - 19

Contractor:

PMF

WP owner:

Jaceq

Progress:

Backlog

Finishweek:

37

WP Number:

498

Description:

Cable installation Substation 3 - MCC

Impact on later execution period

Cost impact:

Manhours
Equipment
Others
bottom of page