Workpackages

Installation of purge infeed system

398

Hakan

06-Chip/RC1P feed System - 20

Finishweek:

38

Backlog

PMF

Installation of Instruments

399

Hakan

06-Chip/RC1P feed System - 20

Finishweek:

38

Backlog

PMF

B: Connection B to Reactor

400

Hakan

06-Chip/RC1P feed System - 20

Finishweek:

38

Backlog

PMF

Feed system installation

401

Hakan

06-Chip/RC1P feed System - 23

Finishweek:

39

Backlog

PMF

B: Connection B to Reactor

402

Hakan

06-Chip/RC1P feed System - 23

Finishweek:

39

Backlog

PMF

B: Connection A to Reactor

403

Hakan

06-Chip/RC1P feed System - 23

Finishweek:

38

Backlog

PMF

Feed system installation

404

Hakan

06-Chip/RC1P feed System - 24

Finishweek:

39

Backlog

PMF

B: Connection B to Reactor

405

Hakan

06-Chip/RC1P feed System - 24

Finishweek:

39

Backlog

PMF

B: Connection A to Reactor

406

Hakan

06-Chip/RC1P feed System - 24

Finishweek:

39

Backlog

PMF

E-stop bridges

407

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Fiberglass installation ControlRoom MCC 4-1

408

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable connection MCC-RIO-A

409

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Profinet connections

411

Danny

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable connection MCC-SIS CABINET

412

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-G

413

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Mechanical connections underneath

414

Danny

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable connection MCC-SIS CABINET

415

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-G

416

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-A

417

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Fiberglass installation ControlRoom MCC 3-1

418

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable connection MCC-RIO-G

419

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Fiberglass installation ControlRoom MCC 4-2

420

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable connection MCC-RIO-G

421

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-B

422

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-B

423

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Fiberglass installation ControlRoom MCC-M10

424

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable connection MCC-RIO-B

425

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-B

426

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-SIS CABINET

427

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-SIS CABINET

428

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-A

429

Jaceq

07-Electrical and instrumentation -

Finishweek:

44

Backlog

PMF

Cable connection MCC-RIO-G

430

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-G

431

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

E-stop bridges

432

Danny

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable connection MCC-SIS CABINET

433

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-B

434

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Fiberglass installation ControlRoom MCC 2-7

435

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable connection MCC-RIO-G

436

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-A

438

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Fiberglass installation ControlRoom MCC 3-6

439

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Fiberglass installation ControlRoom MCC 1-6

441

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Fiberglass installation ControlRoom MCC 1-7

442

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Mechanical connections underneath

443

Danny

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Profinet connections

446

Danny

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable connection MCC-RIO-G

447

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

Cable connection MCC-RIO-A

448

Jaceq

07-Electrical and instrumentation -

Finishweek:

37

Backlog

PMF

MCC Emissions Leuhr

449

07-Electrical and instrumentation -

Finishweek:

36

Progress 50

PMF

Cable installation Substation 3 - MCC Oil cleaning

450

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable installation Substation 2 - MCC VRU

451

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

MCC VRU X-X5

453

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable installation MCC Rcb - to users

454

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable installation MCC Emissions to users

455

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

E&I interal Building 2-Entrance bldg (temp)

457

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable tray supports for MCC 15F 1-6

459

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Progress 50

PMF

E&I interal Building 7A rCB proces bldg

460

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable installation Enexis - Substation 3

461

Danny

07-Electrical and instrumentation -

Finishweek:

38

Progress 50

PMF

MCC 4-1 (Oil cleaning)

462

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable installation MCC Oil conditioning to users

465

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

E&I interal Building Substation 3

470

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Progress 50

PMF

Cable installation Substation 2 - MCC Rcb

474

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

E&I interal Building Substation 2

475

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Progress 50

PMF

Cable installation MCC WWT to users

478

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

MCC Oil conditioning 4-2

479

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable installation Substation 2 - MCC WWT

480

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

MCC Oil cleaning 4-1 connections to M08

481

Task

07-Electrical and instrumentation -

Finishweek:

36

Progress 50

Task

Cable installation MCC Oil cleaning to users

482

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

MCC Oil conditioning 4-2

484

07-Electrical and instrumentation -

Finishweek:

36

Progress 50

PMF

MCC RcB 3-1

485

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable installation Enexis - Substation 2

486

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Progress 75

PMF

Cable tray supports for MCC Emissions M10

487

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Progress 75

PMF

Cable installation MCC VRU to users

488

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

MCC WWT 3-6

489

07-Electrical and instrumentation -

Finishweek:

36

Backlog

PMF

Cable installation Substation 2 - MCC Oil conditioning

490

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

E&I interal Building 10-Spotlab (temp)

491

Jaceq

07-Electrical and instrumentation -

Finishweek:

38

Backlog

PMF

Cable installation MCC 1-6 to users

492

07-Electrical and instrumentation - 17

Finishweek:

37

Backlog

PMF

Cable installation Substation 3 - MCC 1-6

493

07-Electrical and instrumentation - 17

Finishweek:

37

Backlog

PMF

MCC 15F 1-6

494

07-Electrical and instrumentation - 17

Finishweek:

37

Backlog

PMF

E&I interal Building 15F Reactor building

495

07-Electrical and instrumentation - 17

Finishweek:

37

Backlog

PMF

MCC 15F 1-6

496

07-Electrical and instrumentation - 17

Finishweek:

37

Progress 25

PMF

Cable installation Substation 3 - MCC 1-7

498

Jaceq

07-Electrical and instrumentation - 19

Finishweek:

37

Backlog

PMF

E&I interal Building 15E Reactor building

499

Jaceq

07-Electrical and instrumentation - 19

Finishweek:

37

Progress 25

PMF

Cable installation MCC 1-7 to users

500

07-Electrical and instrumentation - 19

Finishweek:

37

Backlog

PMF

MCC 15B 2-7

502

Jaceq

07-Electrical and instrumentation - 23

Finishweek:

37

Backlog

PMF

E&I interal Building 15B Reactor building

503

Jaceq

07-Electrical and instrumentation - 23

Finishweek:

37

Backlog

PMF

Cable installation MCC 2-7 to users

504

Jaceq

07-Electrical and instrumentation - 23

Finishweek:

37

Backlog

PMF

MCC 15B 2-7

505

Jaceq

07-Electrical and instrumentation - 23

Finishweek:

37

Progress 25

PMF

Cable installation Substation 2 - MCC 2-7

506

Jaceq

07-Electrical and instrumentation - 23

Finishweek:

37

Backlog

PMF

Supporting E&I

507

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 25

Task

Modifications + Installaton Mixing tanks from Poland

508

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 75

PMF

Blowers ATEX installaton

509

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 25

Task

Prefab piping connections between tanks

510

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 50

PMF

Electrical connections

511

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 25

Task

Piping connections between tanks

513

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Backlog

PMF

MCC installation 4-1 + connections / terminations

514

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 25

Task

Supporting Piping

515

Alain

08-Oil Cleaning (Decanter and Separator)

Finishweek:

40

Progress 25

Task

Piping connections between system

516

Alain

09-Oil Conditioning Unit - M09

Finishweek:

40

Backlog

PMF

Steelwork installation, base frame containers

517

Alain

09-Oil Conditioning Unit - M09

Finishweek:

40

Progress 25

Task

Insulation of Stripper Column from KZU (BRAND)

518

Alain

09-Oil Conditioning Unit - M09

Finishweek:

40

Backlog

Brand

Installation of instruments

519

Alain

09-Oil Conditioning Unit - M09

Finishweek:

40

Backlog

Task

Installation of Stripper Column from KZU

520

Alain

09-Oil Conditioning Unit - M09

Finishweek:

40

Backlog

Task

  • 8