Latest comments

04-09-2025 Cooling screw delay of delivery reported. no update of delivery of Slidevalve and cylinders ( is critical)

224

4 september 2025 om 09:18:22

DJ

04-09-2025 Hydrolic skid in position, Hydrlic subcontracted to Integron execution of work plande week 37

223

4 september 2025 om 09:10:35

DJ

Scrubber installed as per agreement with Circtec, 02-09-2025 requist is made by Circtec to change the alignement of the scrubber executed at 03-09-2025

127

4 september 2025 om 09:07:26

DJ

The initial delivery of the flexible hoses is Circtec scope. Pmf received the requist to support the delivery of these hoses. The delivery time of flexible is 6 weeks and critical. not enough details provided by Circtec to order these in time. PMF ordered flexibles with a deliverytime of 2 weeks in consultation with Simon for first oil. After the test the outlining will be checked by Circtec and recieuwd for the remaining MOD02

121

4 september 2025 om 08:52:51

DJ

Filters are installed The added lines as per P&ID require 5 additional Valves please provide deliverydates and type of valve to be installed.

118

4 september 2025 om 08:47:08

DJ

PMF is informed that the Flange of the spool piece is DN 400 PN6 and the connection required is DN400 PN 10 Cirtec operations informed that the material required is SS310 and deliverytime is 6 weeks. This is a critical item.

32

4 september 2025 om 08:43:22

DJ

No hot nitroges

1

27 augustus 2025 om 15:32:43

Gabriel

Deliverydate kristalex can start week 39

305

14 augustus 2025 om 08:39:03

Arjan

Nee niet aan het bordes SVP, bordes is alleen lopen, geen dynamische krachten

238

12 augustus 2025 om 13:42:21

Arjan

Mag deze aan bordes? graag antwoord Arjan

238

12 augustus 2025 om 13:41:37

Erik

voldoende capaciteit?

618

12 augustus 2025 om 13:30:37

Arjan

Weeknummer geupdate en correct

301

12 augustus 2025 om 13:28:01

Arjan

klopt dit weeknummer wel?

301

12 augustus 2025 om 13:27:04

Gert